A project newly entered into "Construction" phase will not allow me to add additional contacts, i.e. project superintendent and project manager, unless a start date is selected. These contacts are not always known at time of bidding. A notice-to-proceed is not always issued and available at this early stage of construction. The Contractor needs to upload a project schedule before a NTP will be issued so it is somewhat of a catch-22 if the PM has no access. There is typically some "house cleaning," needed at this stage, getting things in order, and preventing the addition of contacts is limiting and a hindrance. It would be helpful if we were allowed to edit the Project Settings without regard to the Start Date or other such restrictions.